Construction of new marine department basin in Haifa port

Ordered By

Port and Railway Authority Haifa Port

Project Overview

The Project "Construction of new marine department basin in Haifa port" requiered a construction of a new key in the length of 175 meters by the use of a 25 meters long combination wall; type AZ-48. Also, a 150 meters long pier was constructed ontop of steel and concrete piles.

Main elements of the project

  • Constracting of 175m of key wall from sheet pile AZ-48.
  • Supply and driving of AZ-48 piles with the length of 22m.
  • Installing of tie rods for anchoring 25m long.
  • Driving of RV piles for anchoring into the old breakwater.
  • Marine dredging .
  • Land reclamation.
  • Salvage of old vessels in the basin.
  • Infrastructure works including electricity, water, fuel, west water etc.
  • Concrete work for capping beam.