Project Overview
The project "Support of GADOT South Jetty at Kishon port" required MAAGAN to supply and install 40 steel pipes in the diameters of 14 " , 24" , 26 " , 28" and in the length of 24 meters on both sides of the pier, and along the existing bridge. Moreover, a new bridge and support columns were construct between the new pier piles. Work was performed by using vibrational driving hammer followed by an impact hammer from a floating barge crane, for rehabilitation and construction of the new support and for the for strengthening of the existing bridge and pipeline bridge.
Main elements of the project
- Supply of pile in the following diameters 40 " 14 " 24 " 26 " 28
- Driving of 40 piles on both sides of the pier to the target depth
- Construction of a new support beam and elements for the new Jetty .