Ordered by
SIPG
Project Overview
The Gulf Port was delivered to a Chinese franchisee for a company called SIPG which received a 25-year franchise for its construction and operation.
The project covers an area of 540 acres for Phase A and 200 additional acres for Phase II.
Start of project - 01.06.2018
Planned completion of project 01.06.2021
The container terminal covers an area of about 340 acres of operating space, 200 acres of administrative space.
The operating area is divided into 10 + 2 beds for container storage, with 2 RMG cranes for each bed.
Also 8 cranes along the STS platform.
The cranes are transported on 13,000m of steel rails installed on concrete foundations.
Main Elements of the project
Earthworks
- Sand Fill - 560,000 cu
- Filling Bedding - 190,000 cu
- Filling recycled material - 175,000 tons.
Infrastructure
- 12,850m of piping for power and communication sleeves in ground wrapped in concrete.
- 8,000m of Communication & Electrical Pipe from steel
- 7,500m drainage pipe with diameters between 400-1200 mm
- 3,600m gravity and drainage sewer pipe.
- 10,800m 250mm fire extinguishing water pipeline.
- 160 hydrants with 2/4 heads.
- 2 fire and sewage pumping stations.
Concrete works
- 50,000 cubic meters of concrete for crane foundations and containers.
- 29 buildings with a total area of 12,000 square meters
- 1 Main building three (3) floors 3,000 sqm
- 1 central garage building 2,500 sqm
- 6 different warehouse structure.
- 6 transformation stations.
- 1 generator structure
- 2 pumping stations.
- 3 service buildings
- 9 different office structure (entrance, exit, train, transport).
Development work
- 24,000m kerb stones.
- 80,000 square meters of paving parking lots and areas with stone paving 6/8/10 cm.
- 145,000 tonnes of asphalt (3-4 layers).
Finishing work
- Coloring roads
- Signage
- 60 checkpoints
- 12 mobile structures for control positions.